Concrete calculator

Slabs, footings, round columns and post holes. Get cubic yards or cubic metres, the number of bags, and whether bags or a ready-mix truck costs less.

Bag yields: QUIKRETE data sheet · Reviewed November 23, 2026
Rule of thumb 5–10%.
Example. Use your store's price.
Ready-mix truck prices
Example. Call local suppliers.

Formulas

  1. Slab / footing: length × width × thickness (in ÷ 12) = cu ft.
  2. Round column: π × (diameter ÷ 2)² × height.
  3. Post hole: π × (hole diameter ÷ 2)² × depth − post cross-section × depth.
  4. Cubic yards = cu ft ÷ 27; m³ = cu ft × 0.0283168.
  5. Bags = cu ft × (1 + waste) ÷ bag yield, rounded up.
Thickness, reinforcement and base prep for driveways, footings and structural elements are set by local code and site conditions. Check with your building department.

FAQ

How many 80 lb bags of concrete make a yard?

One 80 lb bag of QUIKRETE Concrete Mix yields about 0.60 cu ft, so a cubic yard (27 cu ft) takes 45 bags, before waste.

How much concrete for a 10×10 slab 4 inches thick?

10 × 10 × 4/12 = 33.3 cu ft = 1.23 cu yd. That is 56 × 80 lb bags or 75 × 60 lb bags, before waste.

How much extra concrete should I order?

A common rule of thumb is 5–10% to cover uneven subgrade, spillage and form bulging. Running short mid-pour is worse than a little left over.

What about metric bags in Canada?

Choose Canada or 'm'. We include 20 kg and 30 kg bags, with yields derived from the same mix's published density (about 0.47 L per kg). Check the yield printed on your bag.

When is ready-mix cheaper than bags?

Usually once the pour is more than about a cubic yard, but suppliers often have minimum orders and short-load fees. Enter your local prices to compare.